Last week the Sunday Times ran an expose of the UK’s HS2 rail project. The programme is being severely curtailed now due to massive over spending against the budget.

Over several pages, the Times laid out a culture of overspending and bad financial forecasting, with those who tried to point out the problems often forced out or removed if contractors. The accusation is that senior managers knew that budgets were unrealistic but covered up the facts for as long as possible. Presumably that was to keep their lucrative jobs, and keep ministers happy. The thinking may have been that If the programme got to a certain point, then it could not be cancelled.

There was more in yesterday’s edition of the Sunday Times, including an interview with Stephen Cresswell, one of the whistleblowers.

This first phase was expected to cost £21 billion and yet his calculations suggested a fairer assessment was £30 billion — a huge discrepancy. “There were problems with the way the figures had been calculated and it was likely to cost an awful lot more,” he says. “I did the calculations pointing this out but I was told to concentrate my efforts on something else.”

Unfortunately this good piece of reporting did not get much discussion on national TV news certainly, perhaps unsurprisingly given the disaster unfolding in Israel and Gaza.  The report did say that the internal audit function at HS2 is looking into the allegations – but that isn’t good enough. We really need a detailed external review of what happened in HS2, to understand that specific case but more importantly, to see what lessons can be learnt that apply to other large capital programmes in the UK.  Maybe that is best done by the National Audit Office, although several ex-employees have written to the SFO (Serious Fraud Office) accusing HS2 of mismanagement of public funds, so maybe this will all turn more “criminal”. 

If no action is taken quickly, then we will have to see if Labour will have the appetite for driving a review if they do form the next government. After all, it was Labour and Lord Adonis, then Transport Minister, who kicked off HS2 and Adonis was a non-exec of HS2 for some years. But we really do need a review. We can’t allow huge expenditures where the people involved and responsible are pursuing their own goals rather than the taxpayers’ best interests. As Cresswell put it: “Costs, risks, timescales and benefits are being manipulated to suit individuals or organisational goals rather than the public interest”.

Another interesting point the Sunday Times highlighted last week is that Ministers appear to have lied to Parliament – or at best “misled” the house. Chirs Grayling was one, but a junior Minister is also accused.

“ On June 7, 2019, Cook sent a first draft of his report to Grayling. It suggested HS2 was billions of pounds over budget and years behind schedule.….  In July, the minister for transport, Nusrat Ghani, fielded questions during a Westminster Hall debate on HS2 before the Commons final vote on the bill to approve the Birmingham to Crewe phase two leg.  She said: “I stand here to state confidently that the budget is £55.7 billion and that the timetable is 2026 and 2033.” She repeated her assurances five days later, during the third reading debate in the Commons.

An FOI request exposed that she had been told 3 months earlier that the programme would breach its budget – so doesn’t that sound like lying to Parliament?  

It was good to see the shadow Chancellor, Rachel Reeves, announcing that a “covid corruption commissioner” will look into PPE procurement during the pandemic and the waste of billions of public money. In terms of waste, HS2 is at least on that scale, so surely that also deserves a very thorough and independent look at what happened there?

In recent weeks, it feels like I have been writing about pretty serious topics here – HS2, social value, fraud, failures in local government procurement in the UK and the like. So a story I saw recently was attractive as a topic because it wasn’t a matter of life, death or wasted taxpayer money. It was however (allegedly) about a waste of multi-millionaire rock star money. It was also an illustration of a key point that is forgotten surprisgly often when we’re writing specifications and talking to suppliers.

The band Coldplay has gone through an interesting critical trajectory. The hip and trendy NME made A Rush of Blood to the Head album of the year in 2002; but over the years, many started seeing them as purveyors of somewhat dull, middle-aged music. I’ve always thought they were fine songwriters although recent material is a little MOR for my tastes. But what no-one can deny is the level of their success – over 100 million albums sold and still the 14th most listened to band on Spotify today.

For some 22 years, their manager was Dave Holmes. Little is known about him, but more is coming out now as he and the band are busily suing each other. He started legal action in the summer, claiming £10 million from Coldplay in commission on earnings that (he sasy) they have not paid him. But the counter-case from the band is looking for £14 million from him, saying that he has wasted millions of their money. 

And this is where it gets Bad Buying interesting. Much of the claim is around preparation for the huge global Music of the Spheres tour, for which Holmes held ultimate responsibility. By the way, that tour took $617.8 million in ticket sales alone. (Ever thought you are in the wrong business?)  The band claims that costs escalated  and say that equipment was not suitable or was bought at inflated prices. As the Times reported;

Examples in the claim are eye-watering. They include, “16 bespoke stage pylons” for lighting and video that, it allegedly soon became apparent, would be unjustifiably expensive to even use. However, it was too late — €10.6 million had already been chucked at the pylons.

A “visual project known as Jet Screen” was commissioned for $9.7 million, with a huge chunk of that cost, the band claim, personally authorised by Holmes. The problem was that … the dimensions given to the manufacturers for the Jet Screen were wrong — and it was too big. It was only used for ten concerts in Buenos Aires.

Yes, it’s another “Irish government printer” faulty specification story!  In the Bad Buying book, we have the case study of the Irish government buying a state of the art printing machine that simply did not physically fit into the building that was supposed to house it. That was a reminder that sometimes getting the specification right is not a matter of highly complex technology or difficult outcome-based definitions – it can be as basic as the physical measurements!

The Times draws a parallel with the classic Stonehenge scene in the best comedy film of all time, Spinal Tap, where the band commission a model to use on stage – and when it is delivered, it turns out to be tiny. But in this case, the Jet Screen was just too big.

Holmes is also accused of not opening “the shared online Dropbox which contained the designs for the Music of the Spheres Tour at any time between August 2020 and February 2022”.  Rock and roll madness right there! More interesting is his relationship with Live Nation, the promoters of the tour. Holmes had taken loans from Live Nation at what look like preferential terms and the band say he owed some £27.5 million when he was negotiating terms for the tour with the firm. This, say Coldplay, was an inherent conflict of interest, and if those facts are acccurate, that does have some validity in my opinion. It is an interesting situation without a doubt – I certainly wouldn’t want one of my procurement managers negotiating with a supplier if she owed them money.

So we’ll see what happens next. And just remember, if you’re buying anything in the equipment line, just make sure you know how big you really want it to be! Many elements of the specification may be much more complex in many situations, but let’s face it – size really does matter.

It was tempting to write again about the HS2 rail programme given recent events and the question of whether it is going to ever get to Manchester – or indeed to Euston.  It will go down in history as one of the great British public sector disasters, perhaps costing us even more than NPfIT, the NHS IT programme a decade or more ago which certainly cost us billions.  From the very beginning, it was clear to me that the business case was a con in order to justify the programme, which was enough for me to think it was a misjudged idea.

But the wider question is this – why are we so bad in the UK at capital projects and programmes? A recent article in The Times from chief culture writer Richard Morrison highlighted that failure in the specific area of arts-related building projects. The renovation of the Colston Hall in Bristol – to be renamed the Bristol Beacon – is now expected to cost £132 million, against an initial budget of £48 million. In Manchester, the Aviva studios opens soon, with the price-tag of around £240 million, more than double the original cost estimate. In Edinburgh, the redeveloped National Galleries of Scotland is a relative bargain, a mere £38.6 million, only £22 million over budget.

In East London, there is the new East Bank cultural quarter on the former Olympic Park at Stratford. That was supposed to be £385 million, now we are looking at £628 million and still rising. As Richard Morrison said, we might wonder “what difference this glitzy arts campus will make to ordinary lives in London’s poorest borough”. Political vanity projects in London aren’t new of course. Remember Boris Johnson’s “garden bridge” fiasco?

Is it optimism bias we are seeing time and time again?  Is it simply incompetence in terms of properly defining the specification and carrying out costing exercises up front? Can we just blame inflation?  Is it poor contract management and a lack of control that allows suppliers to escalate prices through the project?  Or lack of control on changes in specification, changes which genuinely cause costs to grow?

The other possibility is conspiracy. It is in everyone’s interest for a project to look like a bargain when it comes to justifying it through the business case process. Your new concert hall (or railway) looks like a good investment at £x whereas it wouldn’t look good at £2x. so the sponsors, the professional services, engineering and construction firms involved, perhaps even local people, all want the case to be approved, so let’s make sure it is estimated at x and not 2x.  Everyone also knows that once it is underway, it is very difficult to stop these projects even as the costs escalate, as we are seeing with HS2 now.

This was discussed in a long running legal case over the new concert hall in Paris, which featured in the Bad Buying book. The dispute between the authorities and the architect, Jean Nouvel, got rather nasty before the case was eventually settled in October 2021.  Here is an extract from the book.

“In 2007, he (Nouvel) was contracted to build the auditorium for €119 million, but the final cost was estimated at €328 by the owners and €534 million by the regional state auditors (which in itself seems like a big discrepancy). Le Monde reported Nouvel saying that the €119 million was quoted purely to match the ceiling set for the public tender, and was not really a genuine cost estimate. He claims that €100,000 per seat was the established cost for similar concert halls, and the €119 million total would have required spending only half that much, so it was never realistic. He also claims that everyone knew that the real cost would be much higher – “this is pretty usual in France in public tenders for cultural projects”, he was quoted as saying. His lawyer also says Nouvel is being made responsible for failures in project management”.

So might HS2 have been a case of a conspiracy to reduce the predicted cost in order to get the project approved?  Is this happening in too many UK projects?  If Labour does win the next election, I would suggest an immediate and wide ranging review of why we seem to be so hopeless at building stuff to budget. You’ll need people who are genuinely independent or maybe folk who will blow the whistle on what really goes on! Because the answer can’t just be “a bit of inflation”. Something is going wrong on far too regular a basis in the UK.